Cao Lanh–An Huu Expressway: Material Supply Secured, Construction Accelerates

Monday, 23/11/2026, 06:27 (GMT+7)

(DTO) After facing delays due to a shortage of stone materials, Component Project 1 of the Cao Lanh–An Huu Expressway is now making significant progress as supplies gradually become available.

Stone materials are being mobilised to the construction site of Component Project 1.

In the final days of November, construction activities on Component Project 1 of Phase 1 of the Cao Lanh–An Huu Expressway construction project have intensified.

Component Project 1 is 16 kilometres long. To date, more than 5 kilometres of roads and bridges have been paved with asphalt concrete. Notably, after An Giang Province agreed to allow the extraction of approximately 267,000 cubic metres of stone under a special mechanism to serve the project, the major bottleneck in aggregate supply has gradually been resolved.

Thousands of cubic metres of stone from quarries in An Giang are transported to the construction site each day, enabling contractors to accelerate the remaining work.

Contractors are stepping up construction of Component Project 1.

Engineer Tran Thanh Lich, a technical officer of Thien An Mechanical Construction Co., Ltd., said that along the section handled by his company, major works such as road surface asphalt concrete paving and the installation of traffic signs have basically been completed. The contractor is now focusing on finishing auxiliary works and traffic safety facilities, while preparing to paint road markings.

Meanwhile, construction has also been accelerated at the Provincial Road 850 interchange, which connects to Component Project 2 in My Hiep Commune. With stone materials arriving at the site, the contractor has quickly mobilised additional personnel and equipment and organised simultaneous construction in a rolling sequence. Work teams are focusing on crushed-stone aggregate base layers, asphalt paving and completing bridges along the main route.

Component Project 1 starts at the connection with the My An–Cao Lanh Expressway (Km0+000) in My Tra Ward and ends at Km16+000 in My Hiep Commune. The project is implemented by the Dong Thap Provincial Traffic Construction Investment Project Management Board, with total investment of VND3.64 trillion from the state budget.

Under the design, the project includes one grade-separated interchange connecting with the My An–Cao Lanh Expressway and 19 bridges, comprising 17 bridges along the expressway and two on the interchange ramps. In addition, approximately 23.052 kilometres of residential frontage roads and 23 transverse drainage culverts are being constructed to ensure regional traffic connectivity, drainage capacity and compatibility with the existing irrigation system.

Currently, with supply bottlenecks gradually being addressed, contractors are mobilising maximum resources and deploying multiple construction teams simultaneously along the entire route. As material deliveries become increasingly secure, the construction site is gaining favourable conditions to accelerate progress, with the aim of completing Component Project 1 by the end of December 2026.

By T. DAT